Project: Unloading, Installation and Commissioning of Hydraulic Press Lines (4×630 T & 1×1300 T) at MG Motors’s Halol, Gujarat Plant.
Challenges:
Achievements:
How we did it:
By employing multiple unloading and lifting equipment including articulated Crane and Forklift simultaneously, besides using Client’s Overhead (EOT) Crane, the press parts were unloaded from Trailers. The 7 heavy packages weighing between 62 T to 170 T were Unloaded on Stool / Beams using 600T Hydraulic Gantry.
The unloading and installation of the Press parts was done simultaneously – the Beds were unloaded at the designated area and installed in the pit using the 600T Gantry. After installation of the beds, the 50T capacity EOT was used to install the tie rod and place the upright over the tie rod.
The slides were installed using EOT and all the Crowns, including the fully assembled Crown of the lead Press weighing more than 200MT, were lifted and installed using the 600T Hydraulic Gantry.